What should an electrical submittal package include?

Short answer

An electrical submittal package should include a transmittal or cover sheet, a table of contents, and the product data, shop drawings and supporting documents for every item — organized by specification section, with the exact catalog numbers and options clearly marked, and any deviations from the specification listed up front. Getting the package complete and clearly organized the first time is what keeps it from coming back for resubmittal.

What a submittal is for

Before materials are ordered and installed on a commercial project, the contractor submits documentation showing that the products they plan to use meet the project specifications. The general contractor and the design team — typically the engineer of record — review it and approve it, return it with comments, or ask for a resubmittal. On electrical projects, that can mean hundreds of products, from switchgear and panels to devices and light fixtures.

Before you start

  • Read the specification’s submittal requirements. Most project manuals have a section that sets out how submittals must be formatted, numbered and delivered.
  • Build a submittal log listing every submittal the specifications require, by section, with due dates.
  • Submit long-lead equipment first. Switchgear, transformers, generators and other equipment with long fabrication times can’t be ordered until they’re approved.

The checklist

1. Transmittal or cover sheet

  • Project name and number
  • Specification section number and title
  • Submittal number and revision number
  • Contractor and general contractor names and contacts
  • Date submitted and date a response is needed
  • Short description of what’s included

2. Table of contents

  • Every item listed, in the same order as the package
  • Fixture or equipment type tags matched to the drawings and schedules

3. Product data (cut sheets)

  • A current manufacturer datasheet for every product
  • The exact catalog number highlighted or marked on each sheet
  • Selected options clearly indicated — voltage, ratings, finish, mounting, accessories
  • Options that don’t apply crossed out, so there’s no confusion

4. Shop drawings (where required)

  • Manufacturer drawings for engineered equipment such as switchgear, switchboards and panelboards
  • Ratings, dimensions and configurations that match the project documents

5. Compliance and deviations

  • A statement that the package complies with the specification, or
  • A clear list of every deviation or substitution, with the reason for each

6. Supporting documents (where required)

  • Listings and certifications
  • Warranty information
  • Installation instructions
  • Samples, if the specification calls for them

7. Final check before sending

  • Every item required by the specification section is included
  • Catalog numbers match between the package, the quote and the order
  • The package follows the project’s required format and file naming
  • It has been reviewed internally before it goes to the general contractor

After you submit

  • Track every submittal — sent, under review, returned and approved — with its due date.
  • Read the response carefully. Common responses include approval with no exceptions, approval with corrections noted, a request to revise and resubmit, and rejection. The exact wording varies by project and reviewer.
  • Answer every comment in a resubmittal, and increase the revision number.
  • Order only what’s approved, and keep catalog numbers consistent between the approved submittal and the purchase order.
  • Keep the approved packages — you’ll need the same product data again for closeout documents.

Common mistakes

  • Sending a datasheet without marking the exact catalog number and options
  • Leaving out deviations and hoping they won’t be noticed
  • Submitting long-lead equipment too late
  • Using an outdated manufacturer datasheet
  • Ordering before the submittal is approved
  • Letting the approved catalog number and the ordered catalog number drift apart

Frequently asked questions

What is an electrical submittal?

Documentation — product data, shop drawings and supporting documents — that shows the products a contractor plans to install meet the project specifications. It’s reviewed and approved before materials are ordered.

What’s the difference between product data and shop drawings?

Product data is the manufacturer’s standard datasheet for a product. Shop drawings are drawings prepared specifically for the project, usually for engineered equipment such as switchgear or switchboards.

Who reviews electrical submittals?

Usually the general contractor first, then the design team — typically the electrical engineer of record — as set out in the project specifications.

Which submittals should go first?

Long-lead equipment such as switchgear, transformers and generators, because it can’t be ordered until it’s approved and fabrication can take months.

What does “revise and resubmit” mean?

The reviewer needs changes before they can approve the package. Address every comment, update the revision number and submit again.