How do you manage long-lead electrical equipment on a project?

Short answer

Identify long-lead items at the bid stage, get current lead times before you commit, and work backwards from the date each item is needed on site to set submittal and order deadlines. Then submit those items first, release orders as soon as they’re approved, confirm ship dates in writing and check them regularly — with a backup plan ready if a date slips.

What counts as long-lead equipment

Long-lead equipment is anything that takes long enough to arrive that it can delay the job if it isn’t ordered early. On electrical projects, that usually includes:

  • Switchgear and switchboards
  • Transformers
  • Generators and automatic transfer switches
  • UPS systems
  • Large or custom panelboards
  • Lighting control systems and specialty fixtures
  • Medium-voltage equipment

Lead times vary by product, manufacturer and market conditions, and they change over time. The only reliable number is a current one from your distributor or manufacturer.

Step 1: Identify long-lead items at the bid stage

Go through the drawings, schedules and specifications while you estimate, and list every item likely to be long-lead. Don’t wait until the job is awarded — by then, weeks may already be gone.

Step 2: Get current lead times before you commit

Ask your distributors for current lead times on each long-lead item as part of their quote, not just prices. Where lead times affect the schedule, note your assumptions in your bid so everyone starts with the same expectations.

Step 3: Work backwards from the need-on-site date

For each item, start with the date it must be on site and work backwards:

  1. Need-on-site date — from the project schedule
  2. Ship date — allowing time for transit and delivery
  3. Release for production — allowing for the manufacturer’s current lead time
  4. Submittal approval — allowing time for review, and for a possible resubmittal
  5. Submittal due date — the date your package must go in

If the math doesn’t work, raise it with the general contractor now, not when the equipment is late.

Step 4: Submit long-lead items first

  • Put long-lead submittals at the front of the queue.
  • Make them complete and clearly marked, so they aren’t returned for missing information.
  • Ask the general contractor and design team to prioritize their review.

Step 5: Release and confirm the order

  • Release for production as soon as the submittal is approved.
  • Get a written order acknowledgment confirming what was ordered and the promised ship date.
  • Check that catalog numbers match the approved submittal exactly.

Step 6: Track and expedite

  • Check in regularly with your distributor or the manufacturer’s rep on each long-lead order.
  • Record every change to a ship date, with the date you were told and who told you.
  • Watch for slips early. A change of a week or two on a promised date is often the first sign of a bigger delay.
  • Keep the general contractor informed whenever a date moves.

Step 7: Have a backup plan

If a critical item slips, options may include:

  • An approved alternative from another manufacturer — which will need its own submittal and approval
  • Temporary or rental equipment, such as a rental generator for temporary power
  • Resequencing work so crews stay productive while you wait

Step 8: Prepare for delivery

  • Confirm delivery details — address, access, delivery window and who will receive it.
  • Arrange offloading and rigging for heavy equipment in advance.
  • Plan storage that protects the equipment until it’s installed.
  • Inspect on arrival and report any damage or missing parts immediately.

Common mistakes

  • Identifying long-lead items only after award
  • Pricing equipment without asking for lead times
  • Letting long-lead submittals wait behind routine ones
  • Accepting a verbal ship date without written confirmation
  • Not noticing a slipping ship date until it’s too late
  • Forgetting to plan the delivery itself

Frequently asked questions

What is long-lead electrical equipment?

Equipment that takes long enough to manufacture and deliver that it can delay a project if it isn’t ordered early — typically switchgear, switchboards, transformers, generators, transfer switches, UPS systems and custom panelboards.

How early should long-lead equipment be ordered?

Work backwards from the date it’s needed on site, allowing for delivery, the manufacturer’s current lead time and submittal review. Then submit and order as early as that plan requires — which usually means as soon as possible after award.

Can long-lead equipment be ordered before the submittal is approved?

Generally, orders are released after approval. Releasing earlier carries the risk that the approved equipment differs from what was ordered. If schedule pressure makes it worth considering, agree the approach with the general contractor and design team first.

What should I do if a ship date slips?

Tell the general contractor right away, ask your distributor or rep for the reason and a firm new date, and look at alternatives — an approved equal, temporary equipment or resequencing the work.

What is an order acknowledgment?

The manufacturer’s or distributor’s written confirmation of an order, showing what was ordered, the price and the promised ship date. Check it against your order and the approved submittal.